  1. <CMD><*1203
  2. ┌────────────────────────────────────────────────┐
  3. │         TUTORIAL:  Project monitoring          │
  4. └────────────────────────────────────────────────┘
  5.  
  6.      In this lesson you:
  7.  
  8.      ■  set a baseline to record original
  9.         project dates, resource work, and
  10.         costs
  11.  
  12.      ■  change the duration of a task and see
  13.         its effect on the Gantt chart
  14.  
  15.      ■  enter some ~actual~2 information
  16.  
  17. ──────────────────────────────────────────────────
  18.                   Press Space bar><CMD>
  19. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
  20.  
  21.      The HiTech project is under way now.
  22.      As with any project, there have been
  23.      changes--even a slip in a milestone.
  24.  
  25.      You've been monitoring the progress of
  26.      the various parts of the project, and
  27.      you're ready to edit your plan to bring
  28.      it up-to-date.
  29.  
  30. ──────────────────────────────────────────────────
  31.                   Press Space bar><CMD>
  32. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
  33.      Planning the booth is taking longer than
  34.      anticipated.  In fact, it's going to take
  35.      20 days rather than the planned 15 days.
  36.  
  37.      So that you can make this change to the
  38.      project, the project file will now be
  39.      loaded for you.
  40.  
  41.      Just sit back for a moment and wait for
  42.      the next Tutorial window.
  43. ──────────────────────────────────────────────────
  44.                   Press Space bar><CMD>
  45. <XFLD><Ctrl5><XFLD><ENDDEF>
  46. 5<HOME><F2><ENTER>HITECH1 <F10><F10><CHOME><CMD><*1412
  47. This is the PERT chart for your project.  Before
  48. you change the duration of any task, you need to
  49. set a ~baseline~2 for the project.
  50. ──────────────────────────────────────────────────
  51.                   Press Space bar><CMD>
  52. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1412
  53. When you set a baseline, HPM records task and
  54. project information, such as start and finish
  55. dates, resource work, and costs.
  56. ──────────────────────────────────────────────────
  57.                   Press Space bar><CMD>
  58. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1412
  59. Later, you can display both the baseline and the
  60. updated plan on the Gantt chart to compare the
  61. original plan (baseline) with the revised plan.
  62. ──────────────────────────────────────────────────
  63.                   Press Space bar><CMD>
  64. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1412
  65. A baseline is so useful for analyzing planned and
  66. revised project information that you should
  67. set a baseline as soon as you've created your
  68. project plan.
  69. ──────────────────────────────────────────────────
  70.                   Press Space bar><CMD>
  71. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1412
  72. Set the baseline now -- before making any more
  73. project changes.  Begin by pulling down the
  74. Other menu and selecting ~Set baseline~2.
  75. ──────────────────────────────────────────────────
  76.                Press F7 and type ~2~2><CMD>
  77. <XFLD><F7>2<XFLD><ENDDEF><CMD><*1412
  78. Because a baseline should be set only once for a
  79. project, HPM displays this warning.  It will set
  80. all baseline dates to the dates that are now in
  81. the project.  Just give HPM your confirmation.
  82. ──────────────────────────────────────────────────
  83.                     Press F10><CMD>
  84. <XFLD><F10><XFLD><ENDDEF><CMD><*1411
  85. Now change the Task form for ~Plan~2 to reflect
  86. the duration you now anticipate for the task.
  87.  
  88. The Tutorial will get the Task form for ~Plan~2.
  89. Just wait a moment for the next Tutorial window.
  90. ──────────────────────────────────────────────────
  91.                   Press Space bar><CMD>
  92. <XFLD><Ctrl5><XFLD><ENDDEF>
  93. <F4><ENTER><CtrlE>PLAN<F10><F3>5<HOME><CMD><*1416
  94. Now move to the ~Duration~2 field.
  95. ──────────────────────────────────────────────────
  96.                 Press Down Arrow><CMD>
  97. <XFLD><DN><XFLD><ENDDEF><CMD><*1416
  98. You enter a new duration of 15 working days.
  99. ──────────────────────────────────────────────────
  100.                      Type ~15.0~2><CMD>
  101. <XFLD>15.0<XFLD><ENDDEF><CMD><*1416
  102. Now confirm that the Task form is complete.
  103. ──────────────────────────────────────────────────
  104.                     Press F10><CMD>
  105. <XFLD><F10><XFLD><CMD><*1412
  106. Now take a look at the Gantt chart for this
  107. project.  You see how the baseline can show
  108. changes to a project plan.
  109.  
  110. Use a speed key to display the Gantt chart.
  111. ──────────────────────────────────────────────────
  112.                    Press Ctrl-G><CMD>
  113. <XFLD><CtrlG><XFLD><CHOME><DN><DN><CMD><*5005
  114. To display baseline
  115. dates, pull down
  116. the Format menu for
  117. ~Timescale display~2.
  118. ────────────────────
  119. Press F5 and type ~4~2><CMD>
  120. <XFLD><F5>4<XFLD><HOME><CMD><*1116
  121. Move the cursor to the current setting of ~Display~2
  122. ~baseline dates in Gantt Chart~2.
  123. ──────────────────────────────────────────────────
  124.               Press Tab three times><CMD>
  125. <XFLD><TAB><TAB><TAB><XFLD><ENDDEF><CMD><*1115
  126. Change the setting to ~Yes~2.
  127. ──────────────────────────────────────────────────
  128.                  Press Left Arrow><CMD>
  129. <XFLD><LFT><XFLD><ENDDEF><CMD><*1115
  130. Confirm that the fill-in is complete.
  131. ──────────────────────────────────────────────────
  132.                     Press F10><CMD>
  133. <XFLD><F10><XFLD>
  134. <DN><DN><DN><DN><DN><DN><CMD><*5005
  135. Now examine the
  136. effect on the
  137. sequential tasks,
  138. ~Plan~2 and ~Build~2.
  139. ─────────────────
  140.  Press Space bar><CMD>
  141. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*5005
  142. The baseline extends
  143. as a dotted line
  144. from the left edge
  145. of the bar to the
  146. new planned start
  147. of ~Build~2.
  148. ─────────────────────
  149.    Press Space bar><CMD>
  150. <XFLD><Ctrl5><XFLD><ENDDEF>
  151. <UP><UP><UP><UP><UP><UP><UP><UP><CMD><*5305
  152. Besides
  153. monitoring
  154. changes to
  155. your plan, you
  156. enter ~actual~2
  157. data as you
  158. learn it.
  159. ────────────────
  160. Press Space bar><CMD>
  161. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1407
  162. Enter actual information about:
  163.  
  164.    ■  cost
  165.    ■  start and finish dates
  166.    ■  work
  167.    ■  durations
  168. ────────────────────────────────────────────────
  169.                 Press Space bar><CMD>
  170. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1415
  171. The Task form is a good place to begin.  Use a
  172. speed key to display Plan's task form.
  173. ───────────────────────────────────────────────
  174.                  Press Ctrl-T><CMD>
  175. <XFLD><CtrlT><XFLD><CMD><*1414
  176. This task gets off to a late start because of
  177. staff vacations. To deal with it, you fill
  178. in the ~Act start~2 field.
  179. ──────────────────────────────────────────────
  180.             Press Down Arrow twice><CMD>
  181. <XFLD><DN><DN><XFLD><ENDDEF><CMD><*1414
  182. Now enter the task's ~actual start~2 date.
  183. ─────────────────────────────────────────────
  184.               Type ~20-Jun-1988~2><CMD>
  185. <XFLD>20-Jun-1988<XFLD><ENDDEF><CMD><*1414
  186. Move to the Act finish field.
  187. ──────────────────────────────────────────────
  188.               Press Down Arrow><CMD>
  189. <XFLD><DN><XFLD><ENDDEF><CMD><*1414
  190. When work on the task is done, you will enter
  191. the task's ~actual finish~  date.  For now,
  192. you leave it alone and move to ~% Complete~2.
  193. ──────────────────────────────────────────────
  194.                   Press Tab><CMD>
  195. <XFLD><TAB><XFLD><ENDDEF><CMD><*1414
  196. Before you finish--while the task is partly
  197. complete--you can track progress by filling
  198. in the ~% Complete~2 field.  HPM uses percent
  199. complete for many calculations including
  200. ~earned value~2.
  201. ─────────────────────────────────────────────
  202.               Press Space bar><CMD>
  203. <XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1412
  204. To track actual costs, you can use these
  205. project windows:
  206.  
  207.      ■ ~Other~2    - Task form, Task list
  208.      ■ ~Resource~2 - Allocations list
  209.      ■ ~Overhead~2 - Project form
  210.      ■ ~Penalty~2  - Project form
  211. ────────────────────────────────────────────
  212.                  Press Esc><CMD>
  213. <XFLD><ESC><XFLD><CMD><*1414
  214. That's enough for this lesson.
  215. ────────────────────────────────────────────
  216.                  Press Esc><CMD>
  217. <XFLD><ESC><XFLD><CMD><*1416
  218. Before you leave, review the major points.
  219. ────────────────────────────────────────────
  220.                  Press Esc><CMD>
  221. <XFLD><ESC><XFLD><CMD><*1206
  222.                 ~In summary ...~2
  223.  
  224.    ■ Set a baseline to keep track of
  225.      revisions to your original project plans.
  226.  
  227.    ■ Enter actual dates, costs, and work
  228.      as you learn them.
  229.  
  230.    ■ Keep track of percent complete of tasks.
  231.  
  232. ──────────────────────────────────────────────────